How to execute this task:
1.Select the desired route from the list of pending records.
2.Then, click on the arrow located next to the button and select the desired option: ▪Activity programming: Select this option to program the maintenance route activity. When clicking on this option, the system will open a screen with all the route activities that will be programmed. ▪Activity execution: Select this option to create the maintenance route activity in the execution step. When clicking on this option, the system will open a screen with all the route activities that will be executed.
3.After selecting one of the options, the system will display a screen with all the maintenance route activities that will be programmed/executed. Click on the button to edit the data of the maintenance route activity:
4.Repeat this operation for the other maintenance route activities.
|