Finishing the maintenance activity |
See how to end the maintenance activity:
1.To finish a maintenance activity, first locate the maintenance that is with the "Execution" status, which can be found by the icon in the S column.
2.After that, click on the button to open the maintenance data in edit mode.
3.In the General data General data section, fill in the fields related to the maintenance execution:
Execution: Enter the data related to the end of the maintenance activity execution: ▪End: Enter the end date of the maintenance. This field may be automatically filled in if the Actual % field has been filled in with 100%. ▪Time: Enter the end time of the maintenance. ▪Duration: This field is filled out by the system with the number of hours the activity was running. ▪Actual %: As soon as the end date is filled in, this field if filled in with 100%. If this field is filled with 100%, the activity execution will be finished, that is, the End date will be filled with the current date.
4.After completing all necessary maintenance execution information, click on the button in the Execution section to send the execution to the next step. The system will ask whether you wish to send the record to the next step.
|