Adding a verification plan |
![]() ![]() ![]() |
See below how to draft a verification plan:
Click on the
▪Inherit activity data: Select this option to create a plan by inheriting data from an existing standard activity. To do this, select the Activity that will be inherited, in the respective fields. When a verification plan is created with this option, the activity data is not shown in the verification plan data, that is, in the verification plan only the plan data can be edited, and the standard activity will be associated with this plan. ▪Copy data from activity: Select this option to copy the data of an activity to the plan activity. To do this, select the Activity that will be copied, in the respective fields. When a verification plan is created with this option, the activity data is incorporated into the plan, that is, the plan data will display the standard activity information, allowing this information to be edited.
1.After defining the plan activity, the system will display the verification plan screen:
|