Resource - Tool |
![]() ![]() ![]() |
Use the Resources
1.
2.Fill in the following fields: Tools: Select the tool (asset) that will be associated with the activity. Sched. quantity: This field will be enabled for standard activity, plan, and activity in planning (programming). Enter the scheduled quantity of the tool that will be used in the activity. Actual quantity: This field will be enabled when the tool association is being made while the activity is running. Use this field to enter the actual quantity of tool that was used in the activity.
3.After filling the fields in, click on the Save button. At this point, the selected variable will be associated with the standard activity in question. |