Navigation:  Management > Resources control >

Editing verification activities

Previous  Top  Next

If it is required to edit any verification information, such as rescheduling the execution period, changing the responsible for the execution, and associating the resources, click on the name of the verification activity in the resource control panel. At this point, a screen containing the verification activity data that can be edited will be displayed.

 

 

(A) To reschedule the period in which the activity is to be performed, complete the Planned start date and Planned end date fields with the dates that will define the new activity execution period.

 

(B) If necessary, it is also possible to change the Description of the activity.

 

(C) To change the performers of the activity, select the new Responsible team for the execution and, if necessary, set the member of this team who will be the specific Executor of the verification.

 

(D) When you click on the Add resource button, a screen will open where the features of the activity in question should be selected.