Navigation:  SE GanttChart > Task >

Cancelling/reactivating a task

Previous  Top  Next

SE GanttChart allows the tasks of the project structure to be canceled/reactivated. The way to perform both operations is similar, because of that, the description will be made in this section only. See how to perform them:

 

1.In the structure, select the task you wish to cancel/reactivate.

 

2.Click on the Cancel/Reactivate option in the Task tab.

 

3.At this time will open the screen for cancellation/reactivation of the task. The WBS, ID #, Name, Date and Options filled are filled by the system with the respective information of the selected task and of the operation being performed. In the Explanation fields enter why the action (cancel/reactivate) is being performed.

 

 

4.After that, save the record. A canceled task can be identified in the S column by the icon. When reactivating a task, it will be again displayed in the chart as usual. Note that a cancelled task does not affect the calculation of the schedule.